The project consists of five (5) wellhead jackets c/w temporary drill decks, riser guards and boat landings, which will be installed offshore Qatar.
The North Field South (NFS) project development will add new offshore wells and infrastructure including wellhead platforms, pipelines, and onshore facilities to boost LNG production for export. The new development will add fifty (50) wells on five (5) offshore platforms (WHPs) located approximately 20 – 30 km from Ras Laffan with a water depth variation of 18 to 24 meters in the North Field. The five (5) WHPs shall feed two (2) LNG mega trains, one pair of WHPs shall support one LNG mega train. Each pair of WHPs are connected through an intrafield pipeline tying into a trunk line.